

Subscribe to Statit Bulletin, our quarterly SPC/Quality Resource
e-newsletter
|
|
 |
Detecting and Correcting
Manufacturing Problems
|
|
 |

Robert F. Hart, Ph. D.
Marilyn K. Hart, Ph.D.
In assembly line manufacturing operations,
problems of poor quality are frequently transient
in nature. For this reason, improvement can
only be made by continuously monitoring the
process and responding promptly by taking corrective
action when the need arises. An effective mechanism
for monitoring the process will be described
below, but it must be kept in mind that the
best monitoring methods become only an idle
exercise unless corrective action is taken when
needed.
A primary roadblock to process improvement
is lack of timely information on manufacturing
problems. All too often, management is totally
unable to answer the questions:
ON
THE PRECEEDING SHIFT, WHAT WAS THE PERCENT DEFECTIVE
(OR DEFECTS PER UNIT)?
WHAT TYPES OF PROBLEMS WERE CAUSING THIS SCRAP
AND/OR REWORK?
The prerequisite to process improvement is
the ability to define opportunities to improve,
sometimes called "problems." The first
line of defense for management is timely, accurate
information on manufacturing problems. As defects
arise, they should first be tallied in real
time. To do this effectively requires the development
and use of tally sheets appropriate to the process.
This frequently calls for the use of a number
of different tally sheet forms, each one tailored
to a specific area on the shop floor. At regular
intervals, no less often than the end of each
shift, the data on one tally sheet is summarized
and transcribed to a single column of a "spreadsheet,"
which may appropriately be called a Percent
Defective (or Defects per Unit) Summary Chart,
discussed in the three references listed at
the end of the article. The problem addressed
here was a problem of dirt in a plastic injection
molding process. Figure 1 is an example of a
tally sheet and Figure 2 is a Percent Defective
Summary Chart.
|
Percent Defective
Tally Sheet
|
| P/N: X42378 |
Name: Bottom Plate |
Machine #: 12 |
| Date: 2/11 |
Shift: 1 |
Operator: J.S. |
| |
| Defect |
Tally |
Totals
|
| Dirt |
1 1 1 1 1 1 1 |
7 |
| Burns |
|
|
| Short |
|
|
| Blisters |
|
|
| Poor Trim |
1 1 1 1 1 |
|
| |
|
|
| Misc. |
|
|
|
Total Number Rejected
|
12
|
|
Total Number Run
|
574
|
|
Percent Rejected
|
2.1%
|
Figure 1. Tally Sheet for Defectives, Shift 1,
February 11

Figure 2. Percent Defective Summary Chart (for
best viewing, you may want to print this article)
As seen in Figure 1, the tally sheet shows
the accumulation during the shift of the defects
of several types. In addition, the total number
of defects, the total number run and the percent
defective for that shift are shown on the tally
sheet. On each shift, one person must be assigned
the task of completing the tally sheet and posting
the results onto the percent defective summary
chart. Since this information is not completely
available until the end of the shift, it means
that the person responsible for posting the
data might (start and) end his work period 30
minutes later than the regular shift.
The results from the tally sheet of Figure
1 are transcribed into the first column of the
Percent Defective Summary Chart of Figure 2,
and the percent defective is recorded on the
graph next to the plotted point. As an alternative,
the shift number may be used as the plotting
symbol. Whatever procedure is used, when multiple
shifts are plotted on the same chart, a distinctive
symbol must be used for each. This is an application
of the general rule that, when unlike things
are plotted on the same chart, classifications
must be clearly noted on the chart.
As shown in Figure 2, the Percent Defective
Summary Chart is not a Shewhart control
chart. It is simply a tabular summary of manufacturing
problems which is updated religiously at the
end of each shift, supplemented by a graph which
shows the overall fraction defective (or number
of defects per unit) for that shift. There is
neither a centerline nor control limits shown
on the graph; the emphasis here is upon the
overview of process performance rather than
upon potentially tedious statistical calculations.
Two important results are immediately clear
from the Percent Defective Summary Chart in
Figure 2.
1.
Dirt is the biggest problem.
2. The problem is on the second shift.
The percent defective summary chart is intended
to be a problem identification tool,
not a problem solving tool. However,
often the clear identification of the problem
leads immediately to the solution. Such was
the case in the real example shown here. Attention
was given to shift-to-shift differences in the
plastic injection processing techniques. Note
that shift 2 has consistently more defects,
primarily from "dirt." After learning
this, the company started looking into the dirt
problem and discovered that dirt was really
a problem on all shifts. Shifts 1 and 3 had
large, powerful men working the shift and they
were strong enough to buff the dirt out. Shift
2 had a slight woman working, so the dirt could
not be buffed out. Obviously, the solution was
not to get a strong man to work Shift 2, but
to eliminate the dirt problem to begin with.
Upon further examination it was found that the
reason the dirt was occurring was a void in
the hopper that was collecting the pellets as
they melted, so some pellets were getting stuck
there, burning, charring, and then flaking off
as dirt. The solution was to fill up that void
and the dirt problem was eliminated. After that,
defects ran less than 1%, with more improvements
continually being made as they became more visible.
Of all the techniques used to maintain and
improve processes, the percent defective summary
chart is the most fundamental, simplest and
most useful. It will tell when to go upstream
for more in-depth detective work (run charts
and control charts) to discover and remove the
root causes for the symptoms which have been
detected.
References
M. Hart, R. Hart, and R. Stanula. "Percent
Defective Summary Chart: Solving a Real Shop
Problem," Journal of Quality Engineering.
14(4) 2002, pp. 547-551.
M. Hart "Quality Tools for Improvement."
Production and Inventory Management Journal,
33(1) 1992, pp. 59-63.
M. Hart and R. Hart. Quantitative Methods
for Quality and Productivity Improvement.
American Society for Quality Control Quality
Press, Milwaukee, Wisconsin, 1989.
For more information, contact Drs. Robert and
Marilyn Hart at robthart@aol.com or (541) 412-0425.
If you would like additional information, please
call our Support staff at (541) 752-4100 or
send email to
.
|
|
|